1. Curing shall commence immediately after the concrete surface is finished. Concrete surface, including the vertical sides, shall be completely covered with curing material.2. Burlap shall be kept continually moistened during the curing period. Polyethylene sheeting or waterproof paper shall be overlapped to prevent moisture loss from concrete. A curing compound may be applied after approval by CONTRACTOR.3. Curing shall be continued for at least 5 days when the temperature is 21°C or higher or for at least 7 days when the temperature is less than 21°C. If the conrete contains high-early strength Portland Cement the curing period shall be reduced to at least 3 days.4. The finished pavement shall be closed to pedestrian traffic for minimum of 3 days and strictly prohibited to vehicular traffic until the concrete has attained its designed compressive strength.