1. Prior to placing concrete, SUBCONTRACTOR shall be notified to CONTRACTOR at least 24 hours in advance.2. Concrete shall be mixed and transported according to Construction Specification for Concrete Work Doc. No. KJG1-PGS-3300-CV-CS-007.3. Before the concrete is placed the granular base shall be moistened. Polyethylene sheeting shall be laid over the moist granular base. Polyethylene sheeting shall be overlapped minimum 10 cm.4. Concrete shall be placed carefully to prevent segregation and displacement of the reinforcement of form work. After spreading the concrete shall be thoroughly consolidated with vibratiors or other approved means.