1. Prior to placing concrete, SUBCONTRACTOR shall be notified to CONTR terjemahan - 1. Prior to placing concrete, SUBCONTRACTOR shall be notified to CONTR Bahasa Indonesia Bagaimana mengatakan

1. Prior to placing concrete, SUBCO

1. Prior to placing concrete, SUBCONTRACTOR shall be notified to CONTRACTOR at least 24 hours in advance.
2. Concrete shall be mixed and transported according to Construction Specification for Concrete Work Doc. No. KJG1-PGS-3300-CV-CS-007.
3. Before the concrete is placed the granular base shall be moistened. Polyethylene sheeting shall be laid over the moist granular base. Polyethylene sheeting shall be overlapped minimum 10 cm.
4. Concrete shall be placed carefully to prevent segregation and displacement of the reinforcement of form work. After spreading the concrete shall be thoroughly consolidated with vibratiors or other approved means.
0/5000
Dari: -
Ke: -
Hasil (Bahasa Indonesia) 1: [Salinan]
Disalin!
1. Prior to placing concrete, SUBCONTRACTOR shall be notified to CONTRACTOR at least 24 hours in advance.2. Concrete shall be mixed and transported according to Construction Specification for Concrete Work Doc. No. KJG1-PGS-3300-CV-CS-007.3. Before the concrete is placed the granular base shall be moistened. Polyethylene sheeting shall be laid over the moist granular base. Polyethylene sheeting shall be overlapped minimum 10 cm.4. Concrete shall be placed carefully to prevent segregation and displacement of the reinforcement of form work. After spreading the concrete shall be thoroughly consolidated with vibratiors or other approved means.
Sedang diterjemahkan, harap tunggu..
Hasil (Bahasa Indonesia) 2:[Salinan]
Disalin!
1. Sebelum menempatkan beton, subkontraktor harus diberitahukan kepada KONTRAKTOR setidaknya 24 jam sebelumnya.
2. Beton harus dicampur dan diangkut sesuai dengan Konstruksi Spesifikasi Doc Kerja beton. Tidak KJG1-PGS-3300-CV-CS-007.
3. Sebelum beton ditempatkan dasar granular harus dibasahi. Terpal polietilen harus diletakkan di atas dasar granular lembab. Terpal polietilen akan tumpang tindih 10 cm minimum.
4. Beton harus ditempatkan secara hati-hati untuk mencegah segregasi dan perpindahan dari penguatan bentuk kerja. Setelah menyebarkan beton harus benar-benar dikonsolidasikan dengan vibratiors atau cara lain yang disetujui.
Sedang diterjemahkan, harap tunggu..
 
Bahasa lainnya
Dukungan alat penerjemahan: Afrikans, Albania, Amhara, Arab, Armenia, Azerbaijan, Bahasa Indonesia, Basque, Belanda, Belarussia, Bengali, Bosnia, Bulgaria, Burma, Cebuano, Ceko, Chichewa, China, Cina Tradisional, Denmark, Deteksi bahasa, Esperanto, Estonia, Farsi, Finlandia, Frisia, Gaelig, Gaelik Skotlandia, Galisia, Georgia, Gujarati, Hausa, Hawaii, Hindi, Hmong, Ibrani, Igbo, Inggris, Islan, Italia, Jawa, Jepang, Jerman, Kannada, Katala, Kazak, Khmer, Kinyarwanda, Kirghiz, Klingon, Korea, Korsika, Kreol Haiti, Kroat, Kurdi, Laos, Latin, Latvia, Lituania, Luksemburg, Magyar, Makedonia, Malagasi, Malayalam, Malta, Maori, Marathi, Melayu, Mongol, Nepal, Norsk, Odia (Oriya), Pashto, Polandia, Portugis, Prancis, Punjabi, Rumania, Rusia, Samoa, Serb, Sesotho, Shona, Sindhi, Sinhala, Slovakia, Slovenia, Somali, Spanyol, Sunda, Swahili, Swensk, Tagalog, Tajik, Tamil, Tatar, Telugu, Thai, Turki, Turkmen, Ukraina, Urdu, Uyghur, Uzbek, Vietnam, Wales, Xhosa, Yiddi, Yoruba, Yunani, Zulu, Bahasa terjemahan.

Copyright ©2024 I Love Translation. All reserved.

E-mail: