If the following conditions apply, namely:(a) the Contractor has diligently followed the procedureslaid down by the relevant legally constituted publicauthorities in the Country,(b) these authorities delay or disrupt the Contractor’swork, and(c) the delay or disruption was Unforeseeable,then this delay or disruption will be considered as a causeof delay under sub-paragraph (b) of Sub-Clause 8.4[Extension of Time for Completion].