The Contractor shall submit a detailed time programme to
the Engineer within 28 days after receiving the notice
under Sub-Clause 8.1 [Commencement of Works]. The
Contractor shall also submit a revised programme
whenever the previous programme is inconsistent with actual progress or with the Contractor’s obligations. Each
programme shall include:
(a) the order in which the Contractor intends to carry out
the Works, including the anticipated timing of each
stage of design (if any), Contractor’s Documents,
procurement, manufacture of Plant, delivery to Site,
construction, erection and testing,
(b) each of these stages for work by each nominated
Subcontractor (as defined in Clause 5 [Nominated
Subcontractors]),
(c) the sequence and timing of inspections and tests
specified in the Contract, and
(d) a supporting report which includes:
(i) a general description of the methods which the
Contractor intends to adopt, and of the major
stages, in the execution of the Works, and
(ii) details showing the Contractor’s reasonable
estimate of the number of each class of
Contractor’s Personnel and of each type of
Contractor’s Equipment, required on the Site for
each major stage.
Unless the Engineer, within 21 days after receiving a
programme, gives notice to the Contractor stating the
extent to which it does not comply with the Contract, the
Contractor shall proceed in accordance with the
programme, subject to his other obligations under the
Contract. The Employer’s Personnel shall be entitled to
rely upon the programme when planning their activities.
The Contractor shall promptly give notice to the Engineer
of specific probable future events or circumstances which
may adversely affect the work, increase the Contract Price
or delay the execution of the Works. The Engineer may
require the Contractor to submit an estimate of the
anticipated effect of the future event or circumstances,
and/or a proposal under Sub-Clause 13.3 [Variation
Procedure].
If, at any time, the Engineer gives notice to the Contractor
that a programme fails (to the extent stated) to comply with
the Contract or to be consistent with actual progress and
the Contractor’s stated intentions, the Contractor shall
submit a revised programme to the Engineer in accordance
with this Sub-Clause.